Example Asbestos Removal Projects in Hawthorne

The seven example jobs below range from a carport ceiling to a full teardown, and from apartment buildings to a single house. Each one shows what was sampled, what came out, how long the work takes and an estimated cost.

Textured carport ceiling removed before new lights go in under an apartment building

Example project

Home
1960s two-story apartment building in Hawthorne with a ground-floor carport under the upper units
Original request
Patch the carport ceiling and hang new light fixtures
Testing
A Cal/OSHA-certified asbestos consultant samples the sprayed texture at three points along the carport
Found
Asbestos in the texture at all three points
Area
About 215 sq ft of carport ceiling
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$2,800

Scope of work

Plastic hung around the work area with air filters running, the texture wetted and scraped into bags, a HEPA clean and the haul. The survey, the district notification fee, the clearance air test, the patching and the new lights are separate.

Project overview

In this example, the owner of a 1960s apartment building in Hawthorne wants new lights under the carport. The old ceiling has a sprayed texture where the fixtures will mount.

The samples all test positive. Because an apartment building is never a single-unit dwelling, the survey comes first and the abatement contractor files the district notice online. The abatement crew scrapes the texture before the electrician arrives.

The goal

The goal is a bare carport ceiling, so the new fixtures mount to a surface with nothing positive left on it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the texture at three points.
  2. Before work The abatement contractor files the district notice online.
  3. Days one and two The work area is walled off with plastic and the texture is wetted and scraped.
  4. Last An independent consultant tests the air, then the electrician mounts the lights.

Planning right

  • Tell residents which parking spaces are closed.
  • Ask the consultant to mark each sample spot on a sketch of the carport.
  • Book the electrician after the air results.
  • Keep the lab report in the building file.

Get a free quoteMore about popcorn ceiling removal

Joint compound removed from a hallway before two new doors are cut in

Example project

Home
1950s single-unit house in El Segundo with a short hallway to three bedrooms
Original request
Cut two new door openings along the hallway for a bedroom suite
Testing
A Cal/OSHA-certified asbestos consultant samples the joint compound and wall texture at both door spots and the hall ceiling
Found
Asbestos in the joint compound at both door spots
Clear
The wall texture and the hall ceiling
Area
About 70 sq ft of hallway wall
Timeline
Less than 100 square feet, so no district notice, then one working day
Cost
$1,900

Scope of work

Plastic over the hall and bedroom doors and a filter running, the positive compound removed wet from both wall sections, bagged disposal and a cleanup. The survey, the framing, the doors and the paint are separate.

Project overview

In this example, a household in El Segundo is adding two doors to the hallway of a 1950s house. A renovation removing less than 100 square feet skips the district notice, and a single-unit house skips the survey requirement, but samples are still how the owners learn what the walls hold.

The joint compound tests positive at both spots and the rest is clear, so the abatement crew takes out the two wall sections and the carpenter cuts the openings afterward.

The goal

The goal is two bare wall sections, so the framers cut into a hallway that holds nothing positive.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the compound, the texture and the ceiling.
  2. Results The report marks the joint compound positive and the texture and ceiling clear.
  3. Work day The hall is sealed and the two wall sections are removed wet.
  4. Then The carpenter frames the new openings.

Planning right

  • Take pictures off the hall walls first.
  • Mark where each door will sit.
  • Leave the sampling to the consultant.
  • Share the report with the carpenter.

Get a free quoteMore about drywall, joint compound and plaster removal

House cleared of positive materials before a teardown for a new two-story

Example project

Home
1950s one-story house in Manhattan Beach with textured ceilings, vinyl in the kitchen and stucco walls
Original request
Tear the house down and build a new two-story on the lot
Testing
A Cal/OSHA-certified asbestos consultant surveys the whole house and the garage, sampling every layer of floor and wall
Found
Asbestos in the ceiling texture, the kitchen vinyl and glue and the hall joint compound
Clear
The stucco and the roof layers
Area
About 2,000 sq ft of ceiling, wall and floor material
Timeline
Notice no later than 10 working days ahead, then four working days before the wrecking crew
Cost
$22,500

Scope of work

Rooms sealed in turn with air filters running, the three positive materials removed wet, labeled bags, air monitoring and the haul with its paperwork. The survey, the district notification fee, the clearance air test, the demolition and the new build are separate.

Project overview

In this example, a family in Manhattan Beach is replacing a 1950s one-story house with a two-story. Every demolition needs the district notice, whatever the size of the house, and the survey comes first.

The ceiling texture, the kitchen vinyl with its glue and the hall joint compound test positive. The abatement crew removes them room by room, and the wrecking crew follows once an independent consultant has tested the air.

The goal

The goal is a house stripped of everything positive, so the wrecking crew starts on a clean site.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant surveys the house and samples each layer.
  2. Before work The abatement contractor files the district notice online.
  3. Days one to four The rooms are sealed one at a time and the three materials come out wet.
  4. Last An independent consultant tests the air, then the wrecking crew starts.

Planning right

  • Ask the abatement contractor for a written work schedule.
  • Keep the survey with the demolition papers.
  • Tell the neighbors the date of the wrecking day.
  • Ask the abatement contractor for the haul paperwork.

Get a free quoteMore about renovation and demolition abatement

Kitchen and hall floors removed in a vacant unit between leases

Example project

Home
1960s twelve-unit apartment building in Hawthorne, one first-floor unit vacant after a move-out
Original request
Lay new flooring in the kitchen and hall before the next lease starts
Testing
A Cal/OSHA-certified asbestos consultant samples the kitchen sheet vinyl and glue and the hall tile and mastic
Found
Asbestos in the kitchen sheet vinyl and its glue
Clear
The hall tile and mastic
Area
About 300 sq ft of kitchen and hall floor
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$3,900

Scope of work

The unit sealed with air filters running, the sheet vinyl lifted and the glue removed wet, bagged disposal and a cleanup. The survey, the district notification fee, the clearance air test and the new flooring are separate.

Project overview

In this example, the manager of a twelve-unit building in Hawthorne has a first-floor unit empty and wants new floors before the next tenant. A unit in an apartment building is never a single-unit dwelling, so the survey comes first, and the job is big enough to need the district notice.

The kitchen vinyl and its glue test positive and the hall floor is clear. The abatement crew works while the unit is empty, and the flooring crew follows after the air results.

The goal

The goal is a bare subfloor in the vacant unit, so the new floor goes in before the next lease with nothing positive under it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the kitchen and hall floors.
  2. Before work The abatement contractor files the district notice online.
  3. Days one to three The unit is sealed and the kitchen floor is lifted and cleaned of glue.
  4. Last An independent consultant tests the air, then the flooring crew starts.

Planning right

  • Move the move-out date into the work plan.
  • Tell the neighbors on the floor about the work days.
  • Keep the report in the unit file.
  • Order the new flooring after the air results.

Get a free quoteMore about floor tile and mastic removal

Kitchen ceiling and floor removed in an upper unit above occupied apartments

Example project

Home
1960s three-story apartment building in Hawthorne, a second-floor unit being remodeled with apartments below and beside it still lived in
Original request
Gut the kitchen and open it to the living room
Testing
A Cal/OSHA-certified asbestos consultant samples the kitchen ceiling texture, the floor vinyl and glue and the wall compound
Found
Asbestos in the ceiling texture and the floor vinyl and glue
Clear
The wall compound
Area
About 300 sq ft, 150 of ceiling and 150 of floor
Timeline
Notice no later than 10 working days ahead, then four working days
Cost
$6,800

Scope of work

The unit sealed at its door with air filters running, the ceiling texture and the floor layers removed wet, bagged disposal carried out on a set route and a cleanup. The survey, the district notification fee, the clearance air test and the remodel are separate.

Project overview

In this example, an owner is remodeling a second-floor unit in a 1960s building while the apartments around it stay occupied. The neighbors get a written schedule before the work starts.

The ceiling texture and the floor layers test positive, and the wall compound is clear. The abatement crew seals the unit and sets the work hours, and the remodel crew starts once the air results are in.

The goal

The goal is a kitchen with the positive ceiling and floor gone, while the other residents keep living in the building.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceiling, the floor and the walls.
  2. Before work The abatement contractor files the district notice online, and the building posts the schedule.
  3. Days one to four The unit is sealed at its door and the ceiling and floor are removed wet.
  4. Last An independent consultant tests the air, then the remodel crew starts.

Planning right

  • Give the neighbors the schedule in writing.
  • Pick the carry-out route before the first work day.
  • Ask the manager which stair and door the crew may use.
  • Hold the cabinet delivery until the air results.

Get a free quoteMore about apartments, condos and commercial suites

Samples taken in a manager’s office before new carpet and paint

Example project

Home
Rental office on the ground floor of a 1960s apartment building in Hawthorne, with carpet over old tile and painted walls
Original request
Replace the carpet and repaint the office walls
Testing
A Cal/OSHA-certified asbestos consultant samples the floor tile and mastic under the carpet, the wall compound and the ceiling
Found
Asbestos in the floor tile and mastic
Clear
The wall compound and the ceiling
Timeline
Lab results first, then the floor removal is planned as its own job ahead of the carpet crew
Estimated testing cost
$550

Scope of work

A visit by the consultant, six samples, a lab result for each and a short report with the sample spots marked. Removing the tile and mastic is priced on its own.

Project overview

In this example, the manager of a 1960s apartment building wants new carpet and fresh paint in the rental office. The carpet comes up over a floor nobody has looked at.

Six samples cover the floor, the walls and the ceiling. Only the tile and mastic test positive, so the walls can be painted as planned and the abatement crew removes the floor layers before the new carpet.

The goal

The goal is a written answer before the carpet goes in, so the floor work is planned instead of discovered.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant lifts a corner of the carpet and samples the floor, walls and ceiling.
  2. Results The report marks the tile and mastic positive and the other materials clear.
  3. Next The abatement crew is booked to remove the floor layers.
  4. Then The carpet crew and the painter schedule after that.

Planning right

  • Move the desk away from the middle of the floor.
  • Do not lift the carpet before the visit.
  • Hold the carpet order until the lab results are in.
  • Add the report to the building file.

Get a free quoteMore about asbestos testing and surveys

Wrapped duct at the furnace removed before a new furnace in an owner’s unit

Example project

Home
1960s fourplex in Hawthorne, the owner living in one unit with a furnace in a hall closet
Original request
Replace the failing furnace in the owner’s unit
Testing
A Cal/OSHA-certified asbestos consultant samples the duct wrap at the plenum, the seam tape and the closet wall
Found
Asbestos in the wrap at the plenum and in the seam tape
Clear
The closet wall
Area
About 35 sq ft of wrap and tape
Timeline
Less than 100 square feet, so no district notice, then one working day
Cost
$2,100

Scope of work

The hall closet sealed with plastic and a filter running, the positive wrap and tape removed and bagged, and a cleanup. The survey, the new furnace and the new duct connections are separate.

Project overview

In this example, an owner who lives in one unit of a 1960s fourplex is replacing the furnace. A fourplex has four units, so it is not a single-unit dwelling and the owner hires an abatement contractor for the work.

Taking out a furnace counts as renovation, and the wrap at the plenum and its tape test positive. The job stays at less than 100 square feet, so no district notice is needed, and the installer arrives after the cleanup.

The goal

The goal is a closet with the old wrap gone, so the installer works on clean duct stubs.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap, the tape and the closet wall.
  2. Results The report marks the plenum wrap and the seam tape positive and the wall clear.
  3. Work day The closet is sealed and the wrap and tape come off and go into bags.
  4. Then The installer sets the new furnace.

Planning right

  • Clear the hall closet the evening before.
  • Tell the installer which materials tested positive.
  • Plan for the heat to be off on the work day.
  • Keep the report with the furnace papers.

Get a free quoteMore about HVAC duct and pipe insulation removal

Request a free asbestos removal quote

We recommend calling, but do feel free to contact us using this form. We'll get back to you with a free, personalized quote or additional questions as soon as possible. We're here to help.

Call (424) 588-6917

Call (424) 588-6917